
Wood in Architecture and Construction - Assignment 4 - Material -Yaqi Liao (2/2)
3. How might the building be disassembled? What components of the building might be re-used?
In terms of re-usability, the whole construction process used lots of prefabricated elements to shorten the total
construction time to 10 months. Slits in the wall elements were used to mount the dowel laminated timber elements of
the storey slabs. In this case, most timber elements are reassembled to a theoretical extent. We could disconnect the
batten and reuse the cladding, frame, facade and so on. However, some of them are hard to re-use such as the spruce
cladding. I noticed some damage on the facade in regard to weathering, which needs to fi x over time. Technically, the
triple-glazing window could be reused as well, but it depended on the condition of the timber window,
5. What joints or systems will cause diffi culty in disassembly?
The system design is easy to assemble and disassemble. The only thing I am worried about is the damage to the spruce
cladding. We could see the change of colour and some damage on the cladding at the moment. All the pre fabric
elements would make the process easier, but the joints between slits in the wall and the slabs should be considered
better during the disassembly process.
1. What percentage of material comes from renewable sources?
Total weight of building: 332721.7521 kg
Percentage of renewable sources in weight:76%(including Spruce Wood, Silver fi r, Dowel laminated timber, Sheep’s wool
and Wood fi bre) Not sure if glass is renewable, if so, it will be 79%.
Density value Area(m2)/
Volume(m3) Weight/ kilograms Percentage
1Flat roof
"Bitumen membrane, two-layer,
granular slate surface 5 mm" 3.0 kg/m² 125.85m² 377.55 4%
Cladding, spruce, tongue-and-groove 27/100
mm 370 kg/m³ 14.4m³ 5328 63%
Square timber, spruce,180/100 mm 370 kg/m³ 0.35m³ 129.5 2%
Timber beam, 220/100 mm, 370 kg/m³ 0.43m³ 159.1 2%
Vapour barrier 1100kg/m³ 0.12585m³ 138.435 2%
Acoustic insulation, sheep’s wool 30 mm 31 kg/m³ 3.78m³ 117.18 1%
Battens, silver fi r, untreated 40/36 mm 430 kg/m³ 5.034m³ 2164.62 26%
2Facade and exterior walls
Cladding
Battens, silver fi r, rough-sawn 30/50 –120 mm 430 kg/m³ 46.44m³ 19969.2 19%
Substructure, battens, spruce, painted black
30/50 mm 370 kg/m³ 1.03608m³ 383.3496 0%
Prefabricated element
"Cladding, spruce, tongue-andgroove,
diagonal 25/80 –150 mm" 370 kg/m³ 116.1m³ 42957 41%
Battens, spruce 430 kg/m³ 1.92m³ 825.6 1%
Thermal insulation, sheep’s wool 31 kg/m³ 135.45m³ 4198.95 4%
Interior cladding, silver fi r 430 kg/m³ 30.96m³ 13312.8 13%
Timber window
silver fi r, sanded smooth 430 kg/m³ 33m³ 14190 14%
insulated triple glazing 45 kg/m² 203.1m² 9139.5 9%
3Interior walls
Dowel laminated timber 100mm 400 kg/m³ 44.8m³ 17920 100%
4Stairs
Spruce 1200/30 mm 370 kg/m³ 2.052m³ 759.24 100%
5Structure
Post, spruce 125/60 mm 370 kg/m³ 11.045m³ 4086.65 59%
Beam, spruce 40/50 mm 370 kg/m³ 7.56m³ 2797.2 41%
6Floor Slab (4 fl oors)
Strap fl oor, silver fi r, rough-sawn,nailed,
tongue-and-groove 27/80 –100 mm timbers
62 mm, between them loam building slabs
430 kg/m³ 77.3m³ 33239 26%
Impact sound insulation, wood fi bre 30 mm " 23.19m³ 5797.5 4%
Dowel laminated timber timber, doweled 180
mm 400 kg/m³ 139.14m³ 55656 43%
Soundproofi ng, sheep’s wool 40 mm 31 kg/m³ 30.92m³ 958.52 1%
Gypsum fi breboard 15 mm 1000 kg/m³ 11.595m³ 11595 9%
Ceiling, silver fi r, untreated 40/35 mm laid at
distance 430 kg/m³ 51.53m³ 22157.9 17%
Acoustic insulation, sheep’s wool 30 mm 31 kg/m³ 23.19m³ 718.89 1%
7Foundation
Concrete 2300 kg/m³ 17.85m³ 41055 65%
Substructure, stainless steel tube | 25/25 mm 7500 kg/m³ 1.98m³ 14875 23%
Gradient compensation, plastic pad, black 5 –
25 mm 0.1 kg/m³ 2.975m³ 0.2975 8%
Bitumen membrane, two-layer, torched 10 mm 3.0 kg/m² 1.19m³ 3.57 0%
Insulation, foam glass 120 mm 115 kg/m² 14.28m³ 1642.2 3%
Vapour barrier 1100kg/m³ 1.19m³ 1309 2%
Dowel laminated timber,doweled 100 mm 400 kg/m³ 11.9m³ 4760 7%
Materials List
Community centre St. Gerold, AT 2009
2. How could this ratio be improved?
From the analysis, it is clear a timber building. It has been
described as 'solid wood was the only building material
used'. Although 75% of the building was made of timber, the
largest amount of concrete (13%) is still unignorable.
The building was located in the mountains, so the
concrete foundation is better for the building's usage. It
might be better to think about green concrete to increase
sustainability. However, generally, I think the material usage
is really good in this example.